WO-K-G Recalculate Projected Hours

WO-K-G Recalculate Projected Hours

Purpose of Program

Use this program to recalculate the labor hours remaining by sequence based on the hours reported to date and percent complete.

General Program Operation

You can only run this program if you have set the “Use Projected or Estimate $ and Hours?” to P for Projected in SD-B. You can limit the work orders to be recalculated by entering a from/thru range of work order numbers, Start and Finish Dates, Job Number and by clearing Status Codes and Priority Codes and entering Work Order Class(es)

Once all filters have been entered, the program will recalculate the hours remaining by sequence based on the hours reported to date and the percent complete. Thus, if a sequence was originally estimated to take 10 hours and now there are 8 hours reported but it is only 50% complete, the estimated hours will be reset to 16 total, leaving a balance of 8 hours remaining to be scheduled. Sequences that are complete or have had no time or quantity or percent complete reported will not he changed. You can compare the original estimated hours to the current projection using WO-L-H